Closed Production Order

Hi team,

We are using NAV 2016 and I have a completed production order I would like to reopen and alter as the wrong material amounts/types were consumed. Is there a way this can be done?

Thanks
Steve

  • You will have to do a modification for this, you have to put consumption and output lines back into the Item journal and post them as positive adjmt. for consumption and negative adjmt. for output lines and then change the status of the finished production order to released and put it back. Needs some work in modification.