Hello all,

In case of different routings using same work center, my observation is MPS planning worksheet puts those orders in reverse alphabetical sequence of product names.

For ex.

There are three orders for three products A, B, & C. The delivery date of all these orders is same.

All these three products need the same work center. Obviously, the operations will take place sequentially, that is one after the other. My observation in this case is, planning worksheet first takes product 'C' for production, then 'B' & then'A'. That planning worksheet uses reverse alphabetical logic while allocating the production slots.

Is there a way to change this criteria (of reverse alphabetical orders) & make 'delivery date' as a criteria for deciding priority & allocation production slots accordingly?

Please reply, Thanks in advance,

Kevivetg

 

 

 

 

 

 