Finite planning problem

Hi,

I have Work Center with Capacity 5. I setup this workcenter as Capacity Constrained.

System Plans only one capacity per day. Not 5.


Parents
  • Hi Valentin,

    I'm not 100% clear on your definition of Capacity 5. On the work centre schedule tab you can define Unit of Measure, Capacity, Efficiency and consolidated calendar. However [Planning] calendar defines the CAPACITY over a period of time. Check that you have capacity defined as 5 in the planning calendar for each day. Check also that you have consolidated calendar = No. Also check the setup and run time unit of measure on the routing for the item.
    Good luck.