BOM components are not included in Planning Worksheet

Good morning, 

I am currently testing out Business Central production capabilities and I am wondering why there are no production orders / orders generated for the components of an item. 

Setup: 

Product A needs to be sold 10x 

Product A must be produced consuming 1x Product B each

Product B mus be produced consuming 1x Product C each 

And for Product C there must be a purchase order. 

I believe if I have a demand forecast of 10x Product A, the planning worksheet should suggest 

  • Purchase Order for 10x Product C
  • Production Order for 10x Product B (using product C as stated in BOM) 
  • Production Order for 10x Product A (using product B as stated in BOM) 

Actual result: 

  • Production Order for 10x Product A 
  • NOTHING ELSE

All items are MTS and Lot for lot. Product A & B have restock policies of production order and Product C has a restock policy of order. 

I feel like I am missing a fundamental concept here. Anyone able to help? 