Production cost calculation

Hi

I have setup a route with 1 operation. On the operation i have 3 resources, but when i estimate my Production cost, i only see the cost for the 1 resource.

I have grouped my 3 resources under a resource group

Resources listed

resource 00002 and 000003 have the Cost categories below

Labour Cost have the below labour cost

Resource Prod have the cost categories below

Manufacturing cost has the below cost

When i do my Estimate on my production order i get the below. Only my PROD resource cost is included

Please guide me in the direction where i must go and investigate, is my thinking correct? or is there another way of achieving what i want to do.

Thanks

Parents
No Data
Reply
  • Having multiple resources in a resource group means you can use any of the resource to perform the operation. it has impact on capacity and resource availability, not in cost. You're still using one of the 3 resources 

    Use parameter No of resources to define multiple resources running together in the same time