Tested. One time setup of 72 hours for 120 ton which is wrong. How do I get the following result? 72 hours - MT1 - 40 tons 72 hours - MT1 - 40 tons 72 hours - MT3 - 20 tons 72 hours - MT3 - 20 tons a total of 6 days (144 hours) as MT1 and MT2 run together. Is AX not suitable for process?
-
Hi Monty, just couple of months now. Thanks for the hint Further question. Let say I group Work center MT1 - capacity of 40 ton MT3 - capacity of 20 ton as MTG1 How do I specify in the route version time for item CPD1 (which takes 72 hours to mix) which uses work center MTG1 Setup time : 72 Run time...
-
How do I setup the following conditions?
Work centers
MT1 - Can mix 40 tons of compound
MT2 - Can mix 40 tons of compound
MT3 - Can mix 20 tons of compound
MT4 - Can mix 20 tons of compound
Items
CPD1 - Compound 1 need to be mixed for 72 hours not matter what work center used
CPD2 - Compound...
-
After passing it to the store keeper, I want he to accept, complete it as appropriate and post as required.These tasks are done from Inventory Management module because of decentralization of authority. Can I do that? .
-
Hi all, In AX 4.0, how do you see a voucher of raw material issued for a production from the inventory? Thanks and regards,
-
Hi, I don't think this can be handled by standard AX. You can give us more information of your manufacturing spec., maybe we can contribute...
-
Thanks, but Where can I view the result of MPS, MRP (which form) ?
-
Hi all, How can I run MPS, MRP in AX 4.0? Thanks,